U.S. District Court Judge Emmett Sullivan has ruled Sunflower Electric Power Corp.’s proposed 895 MW coal-fired Holcomb expansion must complete an environmental review before construction on the project can commence in southwest Kansas.

The ruling handed down Tuesday follows a March decision by Sullivan, which determined the federal government’s Rural Utilities Service (RUS) had failed to complete an environmental impact statement before granting approvals for the proposed $2.8 billion coal-fired power project.

Sunflower spokeswoman Cindy Hertel said the utility's officials are still uncertain how the ruling will affect its project. "We haven't had a chance to look at it, to fully digest it," she told The Associated Press.

Most Popular Articles
Power Topics

Power  |  Transmission & Distribution | Smart Grid | Coal-Fueled Generation | Gas-Fueled Generation | Nuclear GenerationRenewable Energy



Advertisement

How to make the best decisions for your utility during a storm

Find out how you can use operational systems and data to restore power quickly in this brief video from ABB. Learn what kind of data you need, where it is stored across the utility and how you can aggregate it into actionable information to get power restored quickly and improve your SAIDI/CAIDI scores. If you would like to learn more, download this free white paper, "Network management for Smart Grids."

View the Smart Grid Video Archive