PennWell Petroleum Group
PUBLICATIONS EVENTS RESOURCE CENTER BOOKSTORE FINANCIAL PRODUCTS CLASSIFIEDS EQUIPMENT JOBS SUBSCRIBE MEDIA KIT
SUBSCRIBE magazines | e-newsletters
| advanced           Hurricane Watch
site map | about 








Events
November 2008

November 24-25

Muscat, OMN
Phone:: 713 292 1945
Fax:: 713 292 1946
Email
Website

November 25-26
Cernobbio, Lake Como, ITA
Phone:: +44 (0) 1737 855281
Fax:: +44 (0) 1737 855482
Email
Website

November 27
Offshore Energy 2008
Rijkswerf Willemsoord, Den Helder, The Netherlands The Netherlands
Phone:: 010 43 60 112
Fax:: 010 43 68 134
Email
Website

December 2-5
Suntec, SING
Phone:: +44 (0)20 7840 2100
Fax:: +44 (0)20 7840 2111
Email
Website

December 2-4
Prague, CZE
Phone:: +44 207 067 1800
Fax:: +44 207 430 0552
Email
Website

December 3-5
Perth Australia
Website

December 3-4
Galveston, TX USA
Phone:: 713 292 1945
Fax:: 713 292 1946
Email
Website

December 3-5
Kuala Lumpur, MAL
Phone:: +971 (0)4 390 3540
Fax:: +971 (0)4 366 4648
Email
Website

December 3-4
Singapore, SING
Phone:: +44 (0) 207 067 1800
Fax:: +44 (0) 207 430 0552
Email
Website

December 3-5
New Orleans, La. US
Phone:: 216 464 2785
Fax:: 216 464 2768
Website

December 8-9
New York, NY USA
Phone:: 212 686 6808
Fax:: 212 686 6628
Email
Website



| RSS Feed Add RSS Feed


Fast-track MA-D6 near start-up

Offshore

Offshore staff

STAVANGER, Norway -- Reliance Industries' deepwater MA-D6 field offshore India should ship first oil shortly, said Raymond Carlsen, executive VP for Aker Solutions at ONS this week.

The schedule has been one of the tightest for a project of this scope, Carlsen claimed. After discovering the field early in 2006, Reliance was keen to go straight to development, but no new FPSOs were available. After discussions with Aker Solutions - which had been working on the KG-D6 subsea project in the same block - Aker was contracted early last year to provide a converted FPSO. It was charged with supplying and installing the mooring systems, topsides process equipment and subsea production hardware.

"The FPSO has been converted in record time," Carlsen said, "while others have been suffering delays. It left Singapore recently and is now on the field." The vessel has been configured to handle liquids input of 80,000b/d, gas processing at 9 MMcm/d, and gas injection at 3 MMcf/d.

Aker delivered the eight-slot production manifold within eight months and six subsea trees. Subsea/pipeline installations started in January, and involved a fleet of 15 ships.

"To do a fast-track project on this scale," Carlsen said, "you can't copy what you did in the past. You must have access to all kinds of equipment that is normally not there when you want it. We were able to tap into these items via frame agreements that we had with Reliance." Another factor was Aker's new subsea tree manufacturing site in Malaysia.

"You also have to have a customer that is not thinking traditionally," Carlsen added. "These guys [at Reliance] are insistent that everything must follow the plan to the tiniest detail, otherwise it impacts delivery. If we were off from the plan, we would never have been able to deliver on time."

08/28/2008

Page 1 of 1




| RSS Feed Add RSS Feed



Offshore Article Categories:

Vessels
  Production
Equipment & Engineering
  Company News
Drilling & Completion
  People on the Move
Leasing
  E-Technology
Pipeline & Transportation
  Construction & Installation
Subsea
  Geology & Geophysics
Tenders
  Regional Reports
Port of Fourchon
  Top Stories / General Interest
Asia Exclusives
  Africa Exclusives
Finance / Companies
  Exploration / Development
Production / Transportation
 
Oil, Gas & Petrochem Equipment Current Issue Table of Contents
Oil & Gas Journal Current Issue Table of Contents
Oil & Gas Financial Journal Current Issue Table of Contents
Offshore Current Issue Table of Contents
LNG Observer Current Issue Table of Contents


Search Products Buyer's Guide >

Search Industry Specs >

Search Industry Jobs >

Magazine & E-Newsletter Subscriptions >