PennWell Petroleum Group
PUBLICATIONS EVENTS RESOURCE CENTER BOOKSTORE FINANCIAL PRODUCTS CLASSIFIEDS EQUIPMENT JOBS SUBSCRIBE MEDIA KIT
SUBSCRIBE magazines | e-newsletters
| advanced           Hurricane Watch
site map | about 








Events
November 2008

November 24-25

Muscat, OMN
Phone:: 713 292 1945
Fax:: 713 292 1946
Email
Website

November 25-26
Cernobbio, Lake Como, ITA
Phone:: +44 (0) 1737 855281
Fax:: +44 (0) 1737 855482
Email
Website

November 27
Offshore Energy 2008
Rijkswerf Willemsoord, Den Helder, The Netherlands The Netherlands
Phone:: 010 43 60 112
Fax:: 010 43 68 134
Email
Website

December 2-5
Suntec, SING
Phone:: +44 (0)20 7840 2100
Fax:: +44 (0)20 7840 2111
Email
Website

December 2-4
Prague, CZE
Phone:: +44 207 067 1800
Fax:: +44 207 430 0552
Email
Website

December 3-5
Perth Australia
Website

December 3-4
Galveston, TX USA
Phone:: 713 292 1945
Fax:: 713 292 1946
Email
Website

December 3-5
Kuala Lumpur, MAL
Phone:: +971 (0)4 390 3540
Fax:: +971 (0)4 366 4648
Email
Website

December 3-4
Singapore, SING
Phone:: +44 (0) 207 067 1800
Fax:: +44 (0) 207 430 0552
Email
Website

December 3-5
New Orleans, La. US
Phone:: 216 464 2785
Fax:: 216 464 2768
Website

December 8-9
New York, NY USA
Phone:: 212 686 6808
Fax:: 212 686 6628
Email
Website



| RSS Feed Add RSS Feed


Chevron's 3 tcf Piceance project gears up

Oil & Gas Journal

By OGJ editors
HOUSTON, Sept. 4 -- Chevron Corp. has started gas production in the Piceance basin in northwestern Colorado as part of a $7.3 billion project to develop an estimated 3 tcf of gas in the basin over several decades.

Production, begun Aug. 25, is 5 MMcfd from the Cretaceous Williams Fork formation through a 30-in. sales line. Chevron has drilled 82 wells on four pads and is launching work on the fifth and sixth pads. Two rigs are running.

The staged operation will involve drilling, fracturing, and completing 2,000-3,000 gas-condensate wells from multiwell pads on 33,000 acres in Garfield County and installing gas gathering and compression equipment. Chevron has a 100% working interest.

Current production capacity of the facilities is 50 MMcfd, and capacity is intended to build to 400-450 MMcfd in several years. Development drilling began in 2007 with the two purpose-built rigs, and four more rigs are to join them over time.

As many as 22 extended-reach wells are to be completed from a single pad.

Chevron signed a long-term agreement in late 2007 with Enterprise Gas Processing LLC to gather and treat the gas at Enterprise's 750 MMcfd Meeker processing plant (OGJ, Nov. 26, 2007, Newsletter). Extracted liquids are to be transported through Enterprise's Mid-America Pipeline.