Queensland oil shale project still in the wings
 

Rick Wilkinson
OGJ Correspondent

MELBOURNE, Aug. 14 -- Brisbane-based oil shale hopeful Queensland Energy Resources Ltd. (QER) has shunned the Alberta-Taciuk Processor (ATP) revolving kiln oil shale processing technology in favor of the Paraho II technology to develop its vast oil shale deposits along Queensland's east coast.

The company chose Paraho II following assessment of 63 other possible technologies and noting the lessons learned from the company's now decommissioned ATP demonstration plant on the Stuart deposit near Gladstone. This plant is being dismantled, and obsolete components are being sold.

QER acquired most of the assets of the original operator Southern Pacific Petroleum (SPP) from the liquidator in 2004 and shut down the Stuart plant because it did not meet environmental and operating performance standards despite SPP's having produced and sold over a million barrels of shale oil from the deposit during 2000-03.

QER decided the ATP could not be scaled up to commercial scale production, whereas it believes the Paraho II technology can be a commercial proposition.

Next Page

Page 1 of 2



To access this article, go to:
http://www.pennenergy.com:80/pennenergy/en-us/index/articledisplay.content.global.en-us.articles.oil-gas-journal.drilling-production.queensland-oil-shale-project-still-in-the-wings.1.html