Mississippi Power's Kemper plant blows deadline after leak

By Jeff Amy, Associated Press

After a tubing leak in part of its Kemper County power plant, Mississippi Power Co. now says it's unsure when the $7 billion plant will be finished.

 

JACKSON, Miss. (AP) — After a tubing leak in part of its Kemper County power plant, Mississippi Power Co. now says it's unsure when the $7 billion plant will be finished.

With the plant three years behind schedule, the Atlanta-based Southern Co. says it won't meet the latest deadline of mid-March. Mississippi Power will update the schedule and cost of the plant next month.

In a Thursday stock filing, Southern says one of the plant's gasifiers developed leaks on March 9. The two gasifiers convert soft lignite coal into synthetic gas at high pressure and temperature. The gas is burned in turbines to generate electricity.

The utility says a month's delay would cost it $25 million to $35 million. Customers could be asked to pay another $20 million in interest and legal costs.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs