Judge: Duke Energy doesn't owe $350M for scuttled nuke plant

By The Associated Press

A federal judge has ruled Duke Energy doesn't have to pay $350 million sought by Westinghouse Electric Co. over scuttled plans to build a nuclear plant in Florida.

 

CHARLOTTE, N.C. (AP) — A federal judge has ruled Duke Energy doesn't have to pay $350 million sought by Westinghouse Electric Co. over scuttled plans to build a nuclear plant in Florida.

The ruling on Dec. 22 by U.S. District Judge Max Cogburn says Duke Energy owes $34 million in fees and interest for ending the contract for Westinghouse to design and build the Levy County plant.

But Cogburn ruled the additional $352 million sought by Westinghouse fell outside of agreed-upon termination costs in that contract. He said that amounted to development costs for nuclear technology from a separate agreement that Duke Energy lawfully exited.

The Levy County deal was struck in 2008 by Progress Energy, which Duke later bought. The contract was formally ended in 2014 after problems with federal licenses.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs