Tenaska’s advanced natural gas power station to improve resource efficiency

Source: Black & Veatch

Using advanced, high efficiency turbine technology and a recycled water cooling process, the Tenaska Westmoreland Generating Station will produce enough power to meet the energy needs of 925,000 homes.

Black & Veatch has been selected to provide engineering, procurement and construction (EPC) services for a new 925 megawatt natural gas combined cycle power plant. Using advanced, high efficiency turbine technology and a recycled water cooling process, the Tenaska Westmoreland Generating Station will produce enough power to meet the energy needs of 925,000 homes. 

The station is located near Pittsburgh and will supply electricity to customers in Pennsylvania and 12 other Northeastern states that operate in the PJM market. PJM is a regional transmission organization (RTO) that coordinates the movement of wholesale electricity in the Northeast U.S. The generating station addresses growing electric power demands in the region while using the latest air quality controls to meet all state and federal emissions standards.


“Black & Veatch has the reputation for constructing safe and reliable power generating facilities, and a record of completing projects on schedule,” said Nick Borman, Tenaska Senior Vice President, Engineering & Construction. “We are pleased to utilize its power delivery and power plant services for the Tenaska Westmoreland project.”

To maximize efficient water use during power generation, the plant will be able to recycle water through the cooling process multiple times. In addition, two new pipelines to deliver clean-burning natural gas to the plant will be connected to existing regional pipelines. The facility is in the heart of the Marcellus and Utica gas shale fields; as a result it is expected that this local resource will be the primary fuel supply source. The project includes a 500Kv switchyard and switching station as well as 1.5 miles of power transmission lines to connect it to the PJM electric grid.
Using advanced, high efficiency turbine technology and a recycled water cooling process, the Tenaska Westmoreland Generating Station will produce enough power to meet the energy needs of 925,000 homes.

Project construction began in 2016 with commercial operation scheduled in 2018.

“We are leveraging our global expertise in EPC for power generation that provides clients a single point of contact across all phases of the project,” said Ed Walsh, President of Black & Veatch’s power business. “Tenaska is committed to providing its customers highly efficient clean energy while using advanced emissions controls that address environmental air quality.”



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Making DDoS Mitigation Part of Your Incident Response Plan: Critical Steps and Best Practices

Like a new virulent strain of flu, the impact of a distributed denial of service (DDoS) attack is...

The Multi-Tax Challenge of Managing Excise Tax and Sales Tax

To be able to accurately calculate multiple tax types, companies must be prepared to continually ...

Operational Analytics in the Power Industry

Cloud computing, smart grids, and other technologies are changing transmission and distribution. ...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Latest Energy Jobs

View more Job Listings >>

Archived Articles

PennEnergy Articles
2008 | 2009 | 2010 | 2011 | 2012 | 2013

OGJ Articles
2011 | 2012 | 2013

OGFJ Articles
2011 | 2012 | 2013

Power Engineering Articles
2011 | 2012 | 2013

Power Engineering Intl Articles
2011 | 2012 | 2013

Utility Products Articles
2011 | 2012 | 2013

HydroWorld Articles
2011 | 2012 | 2013

COSPP Articles
2011 | 2012 | 2013

ELP Articles
2011 | 2012 | 2013