A dam project to increase hydroelectric lake storage for three southeast Alaska communities is underway after officials sorted out issues related to water levels that hampered progress on construction.

 

KETCHIKAN, Alaska (AP) — A dam project to increase hydroelectric lake storage for three southeast Alaska communities is underway after officials sorted out issues related to water levels that hampered progress on construction.

Crews encountered some difficulties beginning the project due to a warm winter and wet spring that left water levels higher than expected at Swan Lake near Ketchikan, KFSK-FM reported (http://bit.ly/28AomDH). While construction continues, the Southeast Alaska Power Agency's hydroelectric plant will continue generating power for Wrangell, Petersburg and Ketchikan.

Eric Wolfe, SEAPA's director of special projects, told the agency's board that the work would result in a 30 percent increase of water storage at Swan Lake and also increase capacity at SEAPA's other plant at Tyee Lake near Wrangell.

Crews with the Seattle-based construction company Pacific Pile and Marine will be installing large panels along the top of the spillway at Swan Lake this summer.

CEO Trey Acteson said the lake level had made it difficult for crews to begin work.

"I mean they've gotta build, put anchors on, put the safety walkways up, and these were all the functions that had planned to be taken at that time," Acteson said.

Acteson said Ketchikan Public Utilities didn't initially agree to buy more power in an effort to lower the lake so crews could begin work.

A power sales agreement allowed Ketchikan and Petersburg to use their own cheaper electrical sources before purchasing SEAPA electricity. SEAPA had asked KPU to buy more from Swan Lake and use less of its local power resources.

Board member Stephen Prysunka said Wrangell and Petersburg were on board with the project and voiced frustration.

"What bothers me with this is that our community voted overwhelmingly to support this project and to put our lot in with this bond and to make sure that this project moved forward," Prysunka said.

Another SEAPA board member and KPU's electric division manager, Andy Donato, said the utility tried to help lower Swan Lake but also had to worry about its own business plan.

"The unfortunate thing is, I think operating this utility or KPU, KPU also has a business plan," Donato said.

The water levels in the lake have been lowered, but project managers say they are working to protect crews working on top of the dam by reducing the water even further to be prepared for potential heavy rains this summer.

The project is scheduled to finish in October.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Making DDoS Mitigation Part of Your Incident Response Plan: Critical Steps and Best Practices

Like a new virulent strain of flu, the impact of a distributed denial of service (DDoS) attack is...

The Multi-Tax Challenge of Managing Excise Tax and Sales Tax

To be able to accurately calculate multiple tax types, companies must be prepared to continually ...

Operational Analytics in the Power Industry

Cloud computing, smart grids, and other technologies are changing transmission and distribution. ...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Latest Energy Jobs

View more Job Listings >>

Archived Articles

PennEnergy Articles
2008 | 2009 | 2010 | 2011 | 2012 | 2013

OGJ Articles
2011 | 2012 | 2013

OGFJ Articles
2011 | 2012 | 2013

Power Engineering Articles
2011 | 2012 | 2013

Power Engineering Intl Articles
2011 | 2012 | 2013

Utility Products Articles
2011 | 2012 | 2013

HydroWorld Articles
2011 | 2012 | 2013

COSPP Articles
2011 | 2012 | 2013

ELP Articles
2011 | 2012 | 2013