JCP&L completes 15 major distribution line upgrades to help prevent or reduce power outages for electric customers

Source: FirstEnergy

This year, JCP&L plans to invest $4.5 million to enhance the reliability of nearly 100 distribution lines across northern and central New Jersey.

Jersey Central Power & Light (JCP&L) has completed upgrades on 15 major circuits serving nearly 28,000 customers in Burlington, Hunterdon, Mercer, Monmouth, Morris, Ocean, Somerset and Warren counties.

The projects are part of an annual process to proactively identify and upgrade distribution lines across JCP&L's service area.  Through its annual circuit upgrade program, JCP&L audits reliability statistics to identify circuits that require a customized plan to boost their performance.  This year, JCP&L plans to invest $4.5 million to enhance the reliability of nearly 100 distribution lines across northern and central New Jersey.

"Our circuit upgrade program helps enhance service reliability by modernizing our distribution system with equipment that can help prevent or reduce the duration of service interruptions for our customers," said Tony Hurley, vice president of Operations for JCP&L.  "These proactive investments helped JCP&L achieve its best service reliability record in more than a decade last year, including a 33 percent reduction in system outage duration and a 19 percent improvement in customer restoration times.  In addition, our tree trimming and vegetation management programs have reduced tree-related outages more than 38 percent."

Upgrade work includes the installation of more resilient fuses, animal guards and lightning protection devices; enhancing tree trimming efforts; replacing wooden cross-arms at the top of utility poles that are showing signs of wear; and installing fault indicators that help pinpoint problem areas, helping to speed the restoration process if an outage occurs.  The 2016 upgrades also include the installation of automatic tie recloser technology, which allows JCP&L to automatically detect and isolate the location of a fault so the vast majority of customers served by the line can be restored quickly while repairs are made specifically where the damage occurred.

Circuit upgrades were completed in the following counties and municipalities:

  • Burlington – Pemberton Township
  • Hunterdon – Clinton Township and Readington Township
  • Mercer – East Windsor Township and Hightstown Borough
  • Monmouth – Marlboro Township, Middletown Township and Millstone Township
  • Morris – Boonton Township, Jefferson Township, Montville Township, Borough of Mount Arlington and Roxbury Township
  • Ocean – Berkeley Township, Brick Township, Township of Toms River and Lakewood Township
  • Somerset – Bernards Township, Borough of Bernardsville, Borough of Far Hills and Borough of Peapack and Gladstone
  • Warren – Allamuchy Township, Frelinghuysen Township and Independence Township

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Making DDoS Mitigation Part of Your Incident Response Plan: Critical Steps and Best Practices

Like a new virulent strain of flu, the impact of a distributed denial of service (DDoS) attack is...

The Multi-Tax Challenge of Managing Excise Tax and Sales Tax

To be able to accurately calculate multiple tax types, companies must be prepared to continually ...

Operational Analytics in the Power Industry

Cloud computing, smart grids, and other technologies are changing transmission and distribution. ...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Latest Energy Jobs

View more Job Listings >>

Archived Articles

PennEnergy Articles
2008 | 2009 | 2010 | 2011 | 2012 | 2013

OGJ Articles
2011 | 2012 | 2013

OGFJ Articles
2011 | 2012 | 2013

Power Engineering Articles
2011 | 2012 | 2013

Power Engineering Intl Articles
2011 | 2012 | 2013

Utility Products Articles
2011 | 2012 | 2013

HydroWorld Articles
2011 | 2012 | 2013

COSPP Articles
2011 | 2012 | 2013

ELP Articles
2011 | 2012 | 2013