Dominion starts construction on $1.3B Greensville County power station

Source: Dominion Virginia Power

Dominion Virginia Power has begun construction on its 1,588- megawatt Greensville County Power Station, immediately after the Virginia Air Pollution Control Board approved the station's air permit.

Dominion Virginia Power has begun construction on its 1,588- megawatt Greensville County Power Station, immediately after the Virginia Air Pollution Control Board approved the station's air permit.

The air permit issued on June 17th was the last regulatory hurdle the station had to clear before it could start construction.

"This is terrific news for Dominion, its customers, the Commonwealth, Greensville County and all of Southside Virginia," said Paul Koonce, chief executive officer for Dominion's Generation Group. "We are excited about the task ahead and are looking forward to getting this state-of-the art power station operating and providing energy to more than 400,000 customers by 2019."

The power station will be a major boost for the region's economy. In its first year of operation, it is expected to provide up to $8 million in property taxes for Greensville County.  Post-construction economic benefits are projected to amount to about $36 million annually, and about 166 jobs will be supported, with roughly half of these in Greensville County.

Over its expected 36 year life, the station will save Dominion Virginia Power customers about $2 billion as a result of the company not having to purchase power from market sources.

The Greensville County Power Station will be Dominion's second major generation project in Southside.  In April, the company began generating electricity from its Brunswick County Power Station. The 1,358-megawatt combined-cycle facility is located just 5 miles from the Greensville site.

The seven-person air board voted 5-0 to approve the permit, which has the strictest carbon limits in the nation. One member abstained and another was absent.

"The Air Board has approved and the Virginia Department of Environmental Quality has issued a very strict permit, which will require that our station be one of the most efficient and environmentally protective natural-gas fueled power stations in the world," said Pamela F. Faggert, Dominion's chief environmental officer and senior vice president sustainability.

At the peak of construction, the Greensville station will have more than 1,000 workers on site.



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Making DDoS Mitigation Part of Your Incident Response Plan: Critical Steps and Best Practices

Like a new virulent strain of flu, the impact of a distributed denial of service (DDoS) attack is...

The Multi-Tax Challenge of Managing Excise Tax and Sales Tax

To be able to accurately calculate multiple tax types, companies must be prepared to continually ...

Operational Analytics in the Power Industry

Cloud computing, smart grids, and other technologies are changing transmission and distribution. ...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Latest Energy Jobs

View more Job Listings >>

Archived Articles

PennEnergy Articles
2008 | 2009 | 2010 | 2011 | 2012 | 2013

OGJ Articles
2011 | 2012 | 2013

OGFJ Articles
2011 | 2012 | 2013

Power Engineering Articles
2011 | 2012 | 2013

Power Engineering Intl Articles
2011 | 2012 | 2013

Utility Products Articles
2011 | 2012 | 2013

HydroWorld Articles
2011 | 2012 | 2013

COSPP Articles
2011 | 2012 | 2013

ELP Articles
2011 | 2012 | 2013