The turnkey power plant with a total installed electrical generating capacity of 459 megawatts (MW) will be erected in collaboration with the local Julius Berger Nigeria PLC construction company.

The picture shows the Siemens SGT5-2000E gas turbine. Three of these turbines will be supplied for the Azura-Edo power plant in Nigeria.

 

Siemens has received an order for the key components of the Azura-Edo IPP power plant in the south of Nigeria. The turnkey plant with a total installed electrical generating capacity of 459 megawatts (MW) will be erected in collaboration with the local Julius Berger Nigeria PLC construction company. Customer is the independent power provider Azura Power West Africa. Siemens has also been awarded a long-term service contract for maintenance and service of the plant for a period of twelve years. Siemens Financial Services (SFS) has been involved in the structuring of the financing since 2012 and is contributing USD 50 million to partially fund the development, construction and operation of the project’s first phase. The commissioning is scheduled for July 2018.

Siemens will supply three SGT5-2000E gas turbines, three SGen-100A generators as well as the SPPA-T3000 control system for the turbines. The Azura-Edo IPP power plant will be constructed near the town of Benin City, directly neighboring the main gas pipelines in Nigeria. Azura-Edo IPP is part of a planned power plant project by Azura Power West Africa, in which a total capacity of 1.5 gigawatts (GW) is to be installed in several phases.

“This power plant project by Azura Power will strengthen the collaboration between Siemens and Nigeria. We are pleased that our customer is placing its trust in our proven SGT5-2000E gas turbine,” stated Andreas Pistauer, sales head of the region Southern, Western & Central Africa within Siemens Power and Gas. “With the supply of Siemens power plant technology, the long-term service contract and our involvement in the financing of the plant we are supporting our customer Azura Power in its ambitious efforts to expand the power generating capacity of the country."

“Siemens and Julius Berger have a well-deserved reputation for efficiency, precision and end-to-end control of the logistical challenges attendant upon the execution of any large scale power plant,” said David Ladipo, Amaya Capital Partner and Managing Director of Azura Power. “However, what has impressed us the most about both firms is their long term vision and their willingness to work with Azura in a spirit of genuine partnership and collaboration.”

Siemens has received four orders from Nigeria for power plant technology. Three SGT5-2000E gas turbines each were installed in the Geregu I (414 MW) and Geregu II (434 MW) power plants. Two gas turbines of the same model are installed in the power block Afam V (276 MW). Counting this current order for the first phase of the Azura-Edo plant, Siemens supplies eleven SGT5-2000E gas turbines with an overall capacity of 1,583 MW to Nigeria.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Storm Impact Analytics for Utilities

In recent years, increasingly volatile and extreme weather events have significantly impacted the...

Reach New Heights: Six Best Practices in Planning and Scheduling

These 6 best practices have created millions of dollars in value for many global companies. Learn...

Making DDoS Mitigation Part of Your Incident Response Plan: Critical Steps and Best Practices

Like a new virulent strain of flu, the impact of a distributed denial of service (DDoS) attack is...

The Multi-Tax Challenge of Managing Excise Tax and Sales Tax

To be able to accurately calculate multiple tax types, companies must be prepared to continually ...

Latest Energy Jobs

View more Job Listings >>

Archived Articles

PennEnergy Articles
2008 | 2009 | 2010 | 2011 | 2012 | 2013

OGJ Articles
2011 | 2012 | 2013

OGFJ Articles
2011 | 2012 | 2013

Power Engineering Articles
2011 | 2012 | 2013

Power Engineering Intl Articles
2011 | 2012 | 2013

Utility Products Articles
2011 | 2012 | 2013

HydroWorld Articles
2011 | 2012 | 2013

COSPP Articles
2011 | 2012 | 2013

ELP Articles
2011 | 2012 | 2013