Southern Co. expects $240MM in payments over late nuclear plant

ByRay Henry, Associated Press

In this June 13, 2014 file photo shows construction on a new nuclear reactor at Plant Vogtle power plant in Waynesboro, Ga. Southern Co. is facing increasing pressure after announcing an 18-month delay on its nuclear plant in Georgia, a lag that could cost at least $720 million. Georgia regulators are already building a case to make the utility company's shareholder eat some of those losses. (AP Photo/John Bazemore, File)

ATLANTA (AP) — Southern Co. expects the firms building its new nuclear plant in Georgia will pay $240 million in damages if the construction schedule slips another year-and-a-half, power company CEO Thomas Fanning said Wednesday.

Those payments from Westinghouse Electric Co. and Chicago Bridge & Iron Co. would offset roughly a third of the costs Southern Co. could face if its two new reactors at Plant Vogtle were delayed an additional 18 months. Southern Co. subsidiary Georgia Power disclosed the potential delay last week and estimated it could cause another $720 million in financing and ownership costs.

CB&I disputed it was responsible for the delays, while Westinghouse Electric declined to comment.

"We think liquidated damages could offset a great deal of those charges," Fanning said. Southern Co. has not accepted the latest timeline from its contractors, which Fanning said might still be shortened.

Nuclear industry supporters had hoped the new plant in Georgia and a sister project in South Carolina would prove reactors could be built without the delays and cost overruns common years ago. The first new reactor at Plant Vogtle was supposed to start producing power in April 2016, with the second reactor following a year later. The latest schedule would push back those deadlines roughly three years.

The project in South Carolina has seen similar issues.

Beyond paying damages for a late schedule, Southern Co. officials have assumed Westinghouse and CB&I will pay the bulk of building costs caused by delays. The plant's owners and builders are already suing each other over prior financial disputes.

CB&I spokeswoman Gentry Brann disputed Wednesday the firm was responsible for the cost of changes to the project. The plant's owners won federal licenses later than expected, and Brann said redesigns required by regulators triggered additional costs.

"We strongly disagree with the comment that the contractors will bear the cost of changes to the project as there are numerous contractual protections for CB&I for cost increases due to regulatory design changes," Brann said in a statement. Westinghouse Electric spokeswoman Sheila Holt declined to comment because of ongoing lawsuits.

Southern Co. officials had earlier suggested they might seek to build another nuclear plant in Georgia. Fanning was more cautious Wednesday.

"We want to make sure we understand and resolve any of these issues on Vogtle 3 and 4 before we go forward," he said in an interview.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs