NRC issues "yellow" finding to Wolf Creek Nuclear Plant

Source: Nuclear Regulatory Commission 

The Nuclear Regulatory Commission staff has determined that an inspection finding at the Wolf Creek nuclear power plant related to a loss of off-site power event is “yellow,” meaning the issue has substantial safety significance and will result in additional NRC inspections and oversight. The plant, located near Burlington, Kan., is operated by Wolf Creek Nuclear Operating Corp.

On Jan. 13, operators at the plant declared an Unusual Event, the lowest of four levels of nuclear emergency, after the failure of a main generator electrical breaker, followed by an unexplained loss of power to a transformer. This caused the switchyard to lose power, which removed the plant’s connection to the electrical power grid. All safety systems responded as expected and emergency diesel generators automatically powered safety-related equipment.

The NRC conducted an Augmented Inspection and determined that actions by the licensee set the stage for the incident because the company failed to provide adequate oversight of contractors while they performed work that could affect safety-related equipment in April 2011. As a result, the licensee failed to identify that electrical maintenance contractors had improperly connected wires on an electrical component. This allowed an electrical short to prevent transfer of power to a transformer on Jan. 13.

The NRC held a public meeting on March 6 in New Strawn, Kan., to discuss the preliminary results of the Augmented Inspection. Following further review, the NRC staff has concluded that the inspection finding is appropriately characterized as “yellow,” which has been accepted by the licensee.

Under the NRC reactor oversight process, inspection findings are evaluated using a significance determination process and assigned a color indicating its safety significance. Findings with very low safety significance are labeled "green." "White" findings have low to moderate safety significance, "yellow" findings have substantial safety significance, and "red" findings have high safety significance.

The “yellow” finding moves Wolf Creek into the “degraded cornerstone” column of the NRC action matrix, resulting in a higher level of NRC oversight. This is the third highest level of NRC oversight and Wolf Creek joins six other U.S. nuclear units in that column. The position of all nuclear units within the NRC Action Matrix is available on the NRC web site at: http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/actionmatrix_summary.html#am_summary.


Sign up for PennEnergy's eNewsletters
For Email Newsletters you can trust

Email Newsletter icon, E-mail Newsletter icon, Email List icon, E-mail List icon Sign up for our Email Newsletter
For Email Marketing you can trust

Weekly Newscast

 

Whitepapers

Survey Report: Smart Process Applications for a Mobile Workforce

In partnership with PennEnergy Research, OpenText surveyed energy companies in the oil and gas, p...

Top 20 Controls ICS Implementation Guide

Considering the complexity and scope of today’s critical control environment, compliance has beco...

Five Steps to Build an Effective Threat Intelligence Capability

Against today’s mutating threat landscape and sophisticated cybercriminals, security and risk (S&...

Big Data: Business Insight for Power and Utilities

With this paper Microsoft aims to distill the Big Data drivers, challenges, and opportunities for...

Latest Energy Jobs

View more Job Listings >>

Technical Digest

 

Archived Articles

PennEnergy Articles
2008 | 2009 | 2010 | 2011 | 2012 | 2013

OGJ Articles
2011 | 2012 | 2013

OGFJ Articles
2011 | 2012 | 2013

Power Engineering Articles
2011 | 2012 | 2013

Power Engineering Intl Articles
2011 | 2012 | 2013

Utility Products Articles
2011 | 2012 | 2013

HydroWorld Articles
2011 | 2012 | 2013

COSPP Articles
2011 | 2012 | 2013

ELP Articles
2011 | 2012 | 2013