Civil works well under way for the start-up of gas production

Source: OGX 

The civil works at the OGX Gas Treatment Unit (GTU) is moving ahead at a rapid pace in the Parnaíba Basin, in the interior of Maranhão. Most of the equipment manufactured in Brazil and abroad is already being assembled, and important phases of the work have already been completed, such as earthworks and launching of pipelines.

Currently the clusters (sets of production wells) are being assembled, and the final assembly of the tanks, the mechanical assembly of the GTU and the cabling connecting all the equipment is being carried out. The interconnection of the pipelines between the clusters and the GTU for exporting the gas production is also taking place.

In the first production field in the region, Gavião Real, 15 out of the 16 wells scheduled to begin production this year have already been drilled. The first phase of gas production will begin in the fourth quarter, with tests at the GTU and at the MPX Parnaíba Thermoelectric Complex turbines where the gas is destined for. Commercial production will take place at the beginning of 2013.


Sign up for PennEnergy's eNewsletters
For Email Newsletters you can trust


Whitepapers

Reducing the Burden of Local Content Development Compliance

Governments across the world are implementing Local Content Development laws.  To comply and...

Know the Standards for Flash Fire Hazards

NFPA 2112 and NFPA 2113. Two companion standards for workers exposed to flash fire hazards, both ...

Pervasive Governance: Rethinking Traditional Approaches to Information Governance for Oil & Gas

Information is an organization’s most important strategic asset – the “lifeblood” of the organiza...

OSHA 1910.269 Are You Regulation Ready?

Read this Q&A to learn about changes to federal regulations and how to select FR garments for...

Latest Energy Jobs

View more Job Listings >>