Binding open season to expand White Cliffs Pipeline capacity

Source: White Cliffs Pipeline, L.L.C.

White Cliffs Pipeline, L.L.C. ("WCPL") a partially owned subsidiary of SemGroup(R) Corporation (SEMG), is considering an expansion of capacity from Platteville, Colorado to Cushing, Oklahoma to facilitate increasing shipments of crude petroleum from the DJ Basin to the Cushing hub (the "Expansion Project"). WCPL hereby announces a binding open season that will provide an opportunity for shippers to support the Expansion Project by making volume commitments, thereby becoming "Priority Service Shippers."

Highlights of Project

•It is anticipated that the Expansion Project would provide capacity for the transportation of approximately 80,000 bpd of crude petroleum from the DJ Basin and that it could be further expanded to support higher volumes as commitments may dictate.
•Subject to regulatory approval, the committed volumes of Priority Service Shippers would not be subject to pro-rationing under ordinary operating conditions.
•Priority Service Shippers would not be exposed to construction cost risk on their volume commitments.
•It is anticipated that the Expansion Project would be in-service for the transportation of crude petroleum by the first half of 2014. Following pipeline construction, Rose Rock Midstream, LP (RRMS), SemGroup's master limited partnership, will continue in its role serving as the pipeline operator. 

Priority Service Shippers' obligations to ship or pay under the transportation services agreements would commence on the in service date of the Expansion Project.

Open Season Process

Bona fide potential shippers that desire to receive copies of the open season documents, including the throughput and deficiency agreement (the "T&D Agreement"), are required to execute a confidentiality agreement (the "CA") in the form and pursuant to instructions available at:
http://www.semgroupcorp.com/OperationsAndCommodities/CrudeOil/WhiteCliffsPipeline/Open%20Season.aspx

Open season will remain open for 31 days and close at 5:00 P.M. CDT on October 22, 2012 at which time the T&D Agreement must be executed.


Sign up for PennEnergy's eNewsletters
For Email Newsletters you can trust

Email Newsletter icon, E-mail Newsletter icon, Email List icon, E-mail List icon Sign up for our Email Newsletter
For Email Marketing you can trust

Weekly Newscast

 

Whitepapers

Substation Communications Design Legacy to IEC 61850 Best Practices

Two trends, the migration of the electrical grid to the “Smart Grid” and the adoption of Ethernet...

How to Mitigate Risk and Ensure Compliance: Govern Your Documents Accordingly

Too often, organizations hear “information governance” and think “records management” and “compli...

Using Information Intelligence for the Energy Sector

  In this IDC Energy Insights white paper, sponsored by EMC, the author provides an overview...

Enterprise Content Management in the Energy Industry: Increase Safety and Reliability, Reduce Costs and Damages

This Frost & Sullivan white paper looks at the need for enterprise content management to incr...

Latest Energy Jobs

View more Job Listings >>

Technical Digest

 

Archived Articles

PennEnergy Articles
2008 | 2009 | 2010 | 2011 | 2012 | 2013

OGJ Articles
2011 | 2012 | 2013

OGFJ Articles
2011 | 2012 | 2013

Power Engineering Articles
2011 | 2012 | 2013

Power Engineering Intl Articles
2011 | 2012 | 2013

Utility Products Articles
2011 | 2012 | 2013

HydroWorld Articles
2011 | 2012 | 2013

COSPP Articles
2011 | 2012 | 2013

ELP Articles
2011 | 2012 | 2013