Gas pipeline nears completion for Nord Stream

Source: Nord Stream

Nord Stream is entering an intensive period during which its engineers and partners will take key steps towards completing the integrated twin pipeline system capable of transporting up to 55 billion cubic meters (bcm) of Russian gas a year to Europe through the Baltic Sea, for at least 50 years: control systems will be adapted to integrate the twin pipelines into a single automated twin-pipeline gas transport system, at the same time as pipe-laying of the second pipeline is completed and pre-commissioning started.

The two-week process of adapting, testing and certifying the integrated control system for the twin pipelines requires the valves at both Russian and German landfall to be shut, gas from the Portovaya Compressor Station to be stopped and the flow of gas through the pipeline to be temporarily halted. All official notifications and technical preparations for this important work have been completed, and Nord Stream AG confirms that the valves will be closed on 15 April 2012. The adapting has been planned in close co-operation with Nord Stream’s upstream and downstream partners.

After all the required tests have been completed and certifications have been received, it is planned that Nord Stream will re-open the valves towards the end of April. The first of Nord Stream’s twin pipelines has transported to its downstream European partners all the gas nominated and supplied by Gazprom Export. To date this totals approximately 3.5 billion cubic meters (bcm) during the ramp-up phase since becoming operational in November.

In the meantime pipe-laying of the second of the twin 1,224 kilometer pipelines is about to be completed, and the three sections will be joined underwater off the Finnish coast in mid-May and off the Swedish coast in early June. Pre-commissioning and commissioning of the second pipeline will take place over the summer, and the second line is on schedule to become operational as part of the integrated twin-pipeline system towards the end of the year.


Sign up for PennEnergy's eNewsletters
For Email Newsletters you can trust


Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs