Parker Drilling announces delayed completion of new Alaska drilling rigs and increased costs result in asset impairment charge

Source: Parker Drilling

Parker Drilling (NYSE: PKD) announced today that completion of its two new-design Arctic Alaska Drilling Units (AADUs) has been delayed to allow the Company to modify the rigs to meet their design and functional requirements. The need for the modifications was determined as a result of comprehensive safety, technical and operational reviews during recent commissioning activities of these prototype drilling rigs. The modification work will extend the commissioning activities and increase the rigs' total costs.

As a result of the extended construction and commissioning schedule and related increased costs, the two rigs' cost at completion is currently estimated to be $385 million, which includes capitalized interest of approximately $49 million. This cost exceeds the estimated fair value of the rigs based on their projected cash flows. In order to adjust the rigs' values to their estimated fair value, the Company expects to record a pre-tax, non-cash charge in the 2011 fourth quarter of approximately $171 million. This is expected to reduce 2011 fourth quarter after-tax earnings per share by approximately $0.95.

The AADUs represent a new class of drilling rig that incorporates some of the most advanced features available in the global land rig market, including a safety-engineered, state-of-the-art equipment package; a highly automated drilling system; zero-discharge capabilities; and a modular design allowing the entire rig to transport itself in three, fully-enclosed mobile units. "Our intent is to deliver to our customer and to Alaska's North Slope drilling market a more productive drilling rig than what is currently available. We expect the AADUs to establish a new standard of performance for arctic drilling programs," said Parker Drilling President and Chief Executive Officer, David Mannon. "The unique design for these new, technologically-advanced rigs posed engineering, construction and commissioning challenges that have resulted in unanticipated design modifications, delays and cost increases. The actions we are taking are important to meeting the operational and safety objectives we desire. We continue to work diligently toward completion of this project," said Mannon.

Conference Call 

Parker Drilling has scheduled a conference call for 9:00 a.m. CST (10:00 a.m. EST) on Tuesday, January 17, 2012, to discuss these events. Those interested in listening to the call by telephone may do so by dialing (480) 629-9867. The call can also be accessed through the Investor Relations section of the Company's website at http://www.parkerdrilling.com. A replay of the call will be available on the Company's website for 12 months and by telephone from Jan. 17 through Jan. 24 by dialing (303) 590-3030 and using the access code 4507180#.



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs