Ithaca readies for development drilling at Athena; production to start this year

Source: Ithaca Energy

Ithaca Energy Inc. (LON:IAE) (TSX:IAE) reported that the Sedco 704 rig is now being anchored on location over the Athena field in the UK North Sea and is ready to commence an approximate 180-day campaign to drill a fourth production well and a water injector well and complete the three existing wells on the field as producers.

In addition, modification and re-certification of the Floating Production Storage and Offtake (FPSO) vessel BW Athena is well under way in a Dubai shipyard.

The Sedco 704 drilling unit will initially drill one water injection well, followed by a fourth production well (three suspended appraisal wells are to be completed for production as part of this campaign). The four production wells will be installed with downhole submersible pumps to maximize field production rates. Initial production from the field is estimated at a gross rate of 22,500 barrels of oil per day (bopd) (5,062 bopd net to Ithaca). Applied Drilling Technology International (a division of Transocean Drilling UK Ltd) will manage the program on a 'turnkey' basis which is anticipated to last approximately 180 days. Subsea work will follow in Q3 2011, to install field pipelines and subsea manifolds. The Company will update the market as and when drilling and/or completion work reaches key milestones.

The FPSO BW Athena is at dockside in Dubai and preparation works have commenced to re-certify existing equipment and install new equipment. In Q2 2011 the vessel will be 'dry docked' for the installation of a turret mooring section amidships, extending the FPSO by approximately 65ft. Steelwork for the mooring section is being prepared alongside the dry dock. All work is anticipated to be completed in Q3 2011 allowing the vessel to return to UK waters and arrive on location at Athena at end Q3 2011.

Installation of the FPSO vessel to the mooring buoy, as well as, hook up and commissioning will be completed in anticipation of targeted first oil in Q4 2011. Both BW Offshore's Site Office and the Ithaca Representative's Office in Dubai are manned and operational.

John Woods, Ithaca's Chief Development Officer, commented:

"The drilling program at Athena has commenced on schedule enabling the rig to complete its scope of work ahead of other field construction activities. Work on the Athena field remains very much in line with targeted first production from the field in Q4 this year at a gross rate of 22,500 barrels of oil per day. Work on the FPSO in Dubai and the other project construction activities have also all commenced on schedule and within budget giving the project team an excellent start to the New Year."



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs