Suncor completes oil sands upgrader maintenance work

Source: Suncor Energy

Suncor Energy Inc. (TSX:SU) (NYSE:SU) reports that planned maintenance work on one of its two oil sands upgraders (U2) at its oil sands operations near Fort McMurray, Canada, was completed on schedule and the unit has now returned to normal operations. 

Approximately 700 contractors were involved in safely completing the maintenance work, which began in early September. Planned maintenance work is part of the normal course of operations at the company's Oil Sands facilities and scheduled to provide both preventative maintenance and capital replacement to improve operational efficiency and environmental performance. 

The planned maintenance is expected to support safe, reliable operation of upgrading assets as Suncor works to achieve its average oil sands production targets of 280,000 bpd (+/- 5%) in 2010.



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs