Byron Unit 2 begins planned refueling and maintenance outage

April 19, 2010

Source: Exelon

Exelon's Byron Generating Station began its scheduled refueling and maintenance outage for its nuclear power Unit 2 at 11 p.m. on Sunday, April 18.

The outage marks the completion of a 541-day breaker-to-breaker run (continuous operation between refueling outages) for the unit - the longest continuous run for either unit in Byron Station history. Breaker-to-breaker operations are indicative of a high level of equipment reliability and overall plant performance.

"Our employees are committed to performing every work task correctly the first time, thus ensuring the safe and efficient performance of our units," said Dan Enright, Byron site vice president. "Our goal now is to safely complete all the work needed to return the unit to service, preparing it for another 18 months of safe and reliable operation."

During the maintenance outage, workers will perform more than 10,000 activities on a variety of plant components and systems. This includes replacing approximately a third of the reactors fuel assemblies.

The station will utilize the talents and expertise of more than 1,500 additional workers during the outage. The supplemental workers include employees from other Exelon sites as well as contractors. Many of these individuals travel to Byron from outside the area and provide a temporary benefit for the local economy.

Byrons Unit 1 will continue to supply clean electricity to Exelon customers during the Unit 2 outage.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Latest PennEnergy Jobs

PennEnergy Oil & Gas Jobs