880 MW Carrington gas-fired power plant enters key phase

Alstom and DF Energy are set to commence pneumatic testing of the gas pipeline to the high-efficien Carrington cy 880MW Carrington gas-fired, combined-cycle power plant in Manchester.

The pneumatic testing, which is an essential part of the power station's commissioning phase, uses nitrogen under pressure to test pipelines.

Pressure testing will evaluate the capability of the gas piping system to withstand the pressures during normal power station operations.

Alstom will commission the power generating equipment, including two gas turbines, two steam turbines and two heat recovery steam generators.

Planned to be commissioned early in 2016, the facility is expected to generate electricity required to power around a million homes



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...