Flamanville reactor overshadowing prospects for Hinkley Point C

Continuing difficulties with EDF’s European Pressurised Reactor (EPR) technology at a flagship plant in northern France are leading to doubts about the viability of the Hinkley Point C nuclear power plant across the English Channel in the UK.

More faults were highlighted in a leaked report on the Flamanville facility from the French nuclear safety regulator, adding to a warning in April about the reliability of the EPR’s reactor vessel.
Flamanville
Flamanville is already five years behind schedule and the UK’s Treasury is, according to the FT, worried about the technology’s capability for Hinkley Point C.

“I think there are serious questions about the technology,” one unnamed Treasury figure told the FT. “Only if that can be fixed is there a desire to go ahead with it . . . on balance.”

Other officials are, according to the paper, considering dropping EPR altogether in favour of a more reliable reactor type.

China’s President Xi Jinping has a state visit to Britain
and this is expected to help move the project to a more advanced phase. Before then, however, the Treasury must complete a review of Hinkley by its “major projects authority”. While officials expect it to get the green light, one said “it would be unwise to predict either way”.

The agreement with EDF by the British government stipulates that the French company’s shareholders are liable for the viability of the EPR technology until such time as the technology is proven.

“It’s pretty natural that the UK government would want to see that the technology actually works before going ahead,” said one person close to EDF’s Hinkley project based in Paris.



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...