Disputed Indonesian coal-fired power project back on track says president

An Indonesian coal-fired power plant project that has suffered repeated delays could begin construction in April, the nation’s president said this week.

The $4bn, 2 GW ‘mega-project’, Southeast Asia’s largest, is to be built in Batang in Central Java by PT Bhimasena Power Indonesia, a joint venture between coal mining group PT Adaro Energy Tbk and two Japanese firms, Itochu Corp and Electric Power Development Co (J-Power). Indonesia aims to bring the plant online by 2018.

According to reports, land acquisition problems have caused extensive delays to the project, with local farmers objecting on the basis that the site is located within a major rice-growing area. The farmers have so far failed to release 29.8 ha of land to the developers and Arif Fiyanto, Greenpeace Campaign Coordinator, told the Reuters news service that the issue has not yet been resolved.

However, President Joko Widodo (pictured) said yesterday that "The problem regarding the Batang power plant has already been solved. Development will resume next month," adding that "I, myself, have been directly handling the problem."

Since taking office in October 2014, Widodo has said he will make the land acquisition process easier for power and infrastructure project developers. Last month the International Energy Agency said Indonesia must transcend “major barriers” to energy investment and must “take action to increase investment immediately” in order to avoid a power crisis.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...