TenneT connects RWE wind farm to grid

Dutch transmission system operator, TenneT, has successfully commissioned the 576MW HelWin 1 offshore link in the German North Sea.

The Siemens HelWin Alpha converter platform connects RWE’s 295MW Nordsee Ost wind farm and the 288MW Meerwind Süd/Ost owned by WindMW to the grid.
Offshore wind links
HelWin Alpha was constructed by Nordic Yards at its Wismar shipyard and installed in August 2013. Power will be delivered via HelWin 1 to an onshore substation in Büttel through an 85km subsea cable and 45km of onshore lines.

TenneT said the formal handover of HelWin Alpha from Siemens will happen within weeks.

The company also started trial operations for the 690 MW HelWin 2 link today (Tuesday). The HelWin Beta station is sited next to HelWin Alpha and the test run is scheduled to last 10 weeks, ending on 6 April.



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...