Malta-Sicily interconnector reaches testing phase

The 120 kilometre Malta-Sicily subsea interconnector has reached testing phase after a year-long delay.

Enemalta is planning to commission the $216m (€182m) subsea cable, stretching from Qalet Marku in Magħtab to Ragusa in Sicily, by the end of June. The final piece of the jigsaw fell into place last week when the Magħtab Terminal Station was hooked up to the local grid by means of a 6.5 km tunnel excavated to Kappara.
Malta Sicily subsea interconnector
The project is a year behind schedule, due to delays in acquiring planning and environmental permits from the Italian planning authorities.

Measuring 26 centimetres in diameter, the interconnector consists of three single-core 630-square-millimetre copper cables, bound up tightly together with steel wire.

The cable is covered with an additional insulation layer made of lead to prevent any water seeping in. It also houses space for two fibre-optic cables which may be used for data transmission.



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...