Malta-Sicily interconnector reaches testing phase

The 120 kilometre Malta-Sicily subsea interconnector has reached testing phase after a year-long delay.

Enemalta is planning to commission the $216m (€182m) subsea cable, stretching from Qalet Marku in Magħtab to Ragusa in Sicily, by the end of June. The final piece of the jigsaw fell into place last week when the Magħtab Terminal Station was hooked up to the local grid by means of a 6.5 km tunnel excavated to Kappara.
Malta Sicily subsea interconnector
The project is a year behind schedule, due to delays in acquiring planning and environmental permits from the Italian planning authorities.

Measuring 26 centimetres in diameter, the interconnector consists of three single-core 630-square-millimetre copper cables, bound up tightly together with steel wire.

The cable is covered with an additional insulation layer made of lead to prevent any water seeping in. It also houses space for two fibre-optic cables which may be used for data transmission.



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...