Avanzia wins Mexican gas-fired power plant project

Spanish infrastructure company ACS said its Avanzia unit won a $323m contract to upgrade the Tula power plant in Me xico.

It follows Avanzia’s other recent contract wins for the overhauls of the Manzanillo and El Sauz power plants in the Mexican state of Queretaro, ACS said in a statement.

Work on the Tula project will start in February 2015 and is expected to be completed in 29 months for the first combined-cycle gas-fired power unit and 31 months for the second unit, ACS said.

The 638 MW plant is operated by Comision Federal de Electricidad (CFE) and the contract awarded covers engineering, equipment, construction and start-up of the two combined-cycle units, as well as associated services aimed at ensuring Tula's efficient operation, ACS said.



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...