Andritz Hydro wins Norwegian hydropower contract

Austrian hydroelectric power specialists, Andritz Hydro, has been awarded a $55m contract from Lyse Produkcsjon to supplythe electromechanical equipment for the new Lysebotn II hydropower station in Norway.

Under the contract, Andritz Hydro (WBAG: ANDR) will supply two high-pressure Francis turbines with a capacity of 185 MW each, two generator units, hydraulic steelwork and steel linings.
Lysebotn hydropower plant
Lysebotn II, which is planned to be commissioned in spring 2018, will replace the existing Lysebotn hydropower plant and the new hydropower station is expected to increase annual energy production by 14 per cent to reach 1.5 terawatt-hours.

Andritz Hydro said due to the favourable reservoir situation the generating units for the underground hydropower station is designed for frequent start/stop to optimize energy production.

For more hydroelectric power news



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...