First electricity from China’s Ningde nuclear plant

China’s Ningde nuclear power plant has sent electric power to the grid for the first time. The landmark, which was achieved on 28 December, marks the transition of the reactor from the construction to the commissioning phase.

China Guangdong Nuclear Power Company (CGNPC), the plant operator confirmed further tests will be conducted before the reactor will enter commercial operation.

Achieving that status will require regulatory approval, as well as a programme of operational tests including a run lasting 168 hours at its full-rated power output of 1080 MW.

The reactor is the first of four CPR-1000s at the Ningde site in Fujian province. Construction on units 1 and 2 started in 2008 and units 3 and 4 in 2010.

All four reactors are expected to be fully operational before the end of 2015 and will help to ease pressure on the energy transport infrastructure in the congested coastal areas of China's southeast.

Ningde is jointly owned by CGNPC (46 per cent) and China Datang Corporation (44 per cent), with the remaining 10 per cent is held by Fujian Provincial Energy Group.

For more Nuclear Power news.

For more Asia news.



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...