$504m US HEP project on schedule

The US City of Hamilton, Ohio in partnership with American Municipal Power (AMP) has announced that construction on the $504m 105 MW Meldahl Dam hydroelectric power plant is on schedule, with 25 per cent of the project already completed.

Energy Business Review reports that a new transmission line will connect the hydroelectric facility to the existing 345kV Zimmer-Spurlock transmission line in Ohio.

"Once completed, the three turbine units will go on line about 60 days apart, in 2014," said City of Hamilton site representative Tom Leibham.

For more HEP news



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...