1380 MW gas fired power plant approved in China

China Datang International Power Company Limited the listed flagship of China Datang Corporation's 1380 MW Gaojing Gas-fired Thermal Power Plant, has received final approval from the Beijing Municipal Development and Reform Commission.

The project will be entered into its material implementation stage, according to an announcement from China Datang Corporation.

The project is an important step for Datang International in building its thermal power base around the Bohai Sea by introducing leading international technology.

According to the approval, the project will be furnished with three sets of 350 MW, 9FB-type, gas fired, combined-cycle units, together with two 165 MW waste-heat recovery steam turbine generating units (HRSG) with a total installed capacity of 1380 MW and a total heat supply capacity of 963 MW, which is capable of supplying heat for an area of 19 million square kilometers.

According to the schedule, the project will begin operations at the end of 2013.

For more gas fired power news



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...