Alstom-Comelex to overhaul Haiti HEP plant

French firm Alstom-Comelex has received a $49m contract to rehabilitate the existing Peligre hydroelectric power plant in Haiti.

The three-year contract has been awarded by the Haitian government.

The funding has been secured from the Inter-American Development Bank, the German development finance agency, KfW and OFID, and OPEC's fund for international development.

Peligre will recover its original 54 MW generation capacity by implementing an overhaul of its three turbines and modernizing its equipment and control systems.

Currently, the 40-year-old plant uses only a fraction of its potential.

Furthermore, state utility EdH will upgrade the power transmission line connecting the hydro plant with Port-au-Prince as well the capital's electricity distribution network.

The IDB is supporting such investments with grants totaling $32m.

For more hydroelectric power news

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...