Permitting, Costs, Schedule Can Pose Headaches for Developers

When it comes to managing financial risk for electric power infrastructure, a wide array of issues can pose obstacles for project developers, industry officials said during a POWER-GEN panel discussion on Dec. 13.

Risk management in modern project financing can be tough, advised Moxie Energy Vice President Kent Morton. Moxie has led development on a number of combined-cycle gas power plants in the Mid-Atlantic in recent years.

When modeling project expenses, “always assume that it is going to get worse,” Morton said.

“Don’t build a gas turbine that doesn’t have enough gas,” Morton said. “What are the banks going to want,” Morton said.

In addition, it’s important to ensure there are no thorny issues connected with title. Banks love to scrutinize real estate issues, Morton added.

While it is important to identify stakeholders early and identify potential energy project opponents, sometime it’s unwise for a project developer to become visible to the community too early, Morton said.

Most speakers on the panel seemed to agree that permitting risk is increasing these days.

Lenders also care about cost, schedule, performance and other types of risk, said Hunton and Williams attorney Laurence Skinner. “Projects are complicated,” Skinner said. “Everything has to fit together.”

As for schedule, there has to be enough cushion in the planned schedule in case something slips, Skinner said.

Skinner and other speakers said the trend seems to be moving away from the traditional wrapped engineering, procurement and construction (EPC) contract. For example, sometimes the power island is excluded from the EPC contract, officials said.

Insurers and project developers typically like to have one unified insurance package for all the vendors on the property, rather than having everyone bring their own policy, said Paul Healy of Aon Risk Solutions. Insurers also typically want coverage from the time a project is zero percent complete to 100% complete, Healy said.

Some projects are also trying expedited dispute resolution, which can get issues resolved between 30 and 60 days, Healy said.

Safety culture of the companies involved should also be evaluated in the early stages said E3 Consulting President and CEO Paul Plath. The industry average for reported lost-time accidents is 2.1 per 1,000 workers, Plath said.

“How does the operator adopt the best practices in the industry,” Plath said.

Insurers will try to figure out what is a predictable loss for a planned project, said Daniel Mitas of HDR. Of course, every project is different, Mitas said.

Mitas explained that the owners engineer usually work with owners to ensure that a project can pass must technically and regulatory.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...