Wallingford Files Site Plan for 100-MW Addition to Connecticut Power Plant

Wallingford Energy in Connecticut

Wallingford Energy II LLC filed a Development and Management Plan, dated Sept. 2, with the Connecticut Siting Council for the installation and operation of two additional generating units of approximately 50 MW each at the existing generating facility owned and operated by an affiliate, Wallingford Energy LLC.

This plan, with detailed construction drawings and blueprints, was developed in accordance with the council’s conditions of approval for the project. That approval was issued in November 2015.

This extra capacity is being developed primarily to help satisfy capacity and fast-start operating reserve needs in Connecticut and New England. The two additional CTs, referred to as Units 6 and 7, will provide quick-start capacity in the Southwest Connecticut zone, a transmission-congested load pocket within the New England electrical system.

The project schedule at this point calls for an earthwork construction start in March 2017, a mechanical construction start in June 2017 and a commercial operation start for the completed project on April 1, 2018.

The project, consisting generally of two simple cycle aeroderivative combustion turbine generators (CTGs), two SCR/CO emissions control systems, one new BOP switchgear enclosure, one generator step-up transformer, and site work, will reside on a parcel of land leased by Wallingford Energy in Wallingford, Conn., which presently supports five simple cycle General Electric LM6000PC SPRINT aeroderivative gas turbines and appurtenant equipment.

Wallingford Energy leases from the Town of Wallingford approximately 8.5 acres that is currently used for its facility. Pursuant to agreements with the Town of Wallingford, Wallingford Energy II intends to be a sublessee of its project site. The physical footprint of the existing facility covers approximately 4.3 acres of the 8.5-acre site. This new project will utilize approximately 0.9 additional acres of land area on the overall property for the project’s two proposed generating units. Additionally, portions of the broader site will be used for minor relocations of existing equipment and the addition of new project equipment, such as a generator step-up transformer.

The project site is zoned industrial. Land to the north, south and west of the site lies within the industrial district and is mostly developed for industrial uses such as manufacturing, the Town of Wallingford wastewater treatment plant and the town’s capped landfill. Properties to the east of the site, across East Street, are zoned residential. Landscaping, berms and screening walls on the project site and its parent tract help screen views from these non-industrial properties.

Project contact information is: Wallingford Energy II LLC, 400 Chesterfield Center, Suite 110, St. Louis, MO 63017. The company is an affiliate of LS Power.

This article was republished with permission

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Making DDoS Mitigation Part of Your Incident Response Plan: Critical Steps and Best Practices

Like a new virulent strain of flu, the impact of a distributed denial of service (DDoS) attack is...

The Multi-Tax Challenge of Managing Excise Tax and Sales Tax

To be able to accurately calculate multiple tax types, companies must be prepared to continually ...

Operational Analytics in the Power Industry

Cloud computing, smart grids, and other technologies are changing transmission and distribution. ...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...