First Solar EPC Group Surpasses 6 GW of Installed Capacity Worldwide

 First Solar EPC Group Surpasses 6 GW of Installed Capacity Worldwide

First Solar Inc. says its engineering, procurement and construction group has surpassed 6 GW of installed capacity around the world.

Alan Stringer, vice president of Global Project Management and Construction Services, says First Solar installs about 30 to 40 MW per week on 2 GW of active projects.

He says the company’s “manufacturing in the field” concept helps drive down balance of systems costs for customers.

First Solar’s inaugural EPC project was in 2008 with the 10-MW El Dorado Solar Project in Nevada, featuring 220,000 First Solar photovoltaic modules.

In 2015, First Solar completed the 550-MW Desert Sunlight Solar Project and the 550-MW Topaz Solar Farms, each with more than 8 million modules.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now


Making DDoS Mitigation Part of Your Incident Response Plan: Critical Steps and Best Practices

Like a new virulent strain of flu, the impact of a distributed denial of service (DDoS) attack is...

The Multi-Tax Challenge of Managing Excise Tax and Sales Tax

To be able to accurately calculate multiple tax types, companies must be prepared to continually ...

Operational Analytics in the Power Industry

Cloud computing, smart grids, and other technologies are changing transmission and distribution. ...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...