Duke Energy’s Hines Energy Complex Takes Attendees Behind the Scenes

Hines 1

Mild weather and rain didn’t stop the more than 30 POWER-GEN International attendees from loading onto a bus headed to Duke Energy’s (NYSE: DUK) Hines Energy Complex, for an exclusive behind-the-scenes tour.

“I wanted to check out the facility and see what I can learn from them,” said POWER-GEN International attendee, Lee Archer. Archer is representing Portland General Electric during the conference.

Located approximately an hour outside Orlando, in Polk County, Florida, the 1, 912-MW complex is home to four natural gas-fired, combined-cycle units.

The first unit began commercial operation in 1999, and subsequent units began operation in 2003, 2005, and 2007.

Power Block 1 features two Westinghouse Frame 501FCs, one Westinghouse steam turbine, and two Foster-Wheeler heat recovery steam generators (HRSG).

Power Block 2 is comprised of two Siemens Frame 501FD, one Siemens HE steam turbine, and two NEM HRSG. During the tour, attendees were able to take an exclusive look at Power Block 2, because the unit is currently offline for maintenance after a fire broke-out in the unit earlier this year. Power Block 2 is expected to resume operations June 2015.

Power Block 3 includes two Siemens Frame 501FD, one Siemens HE steam turbine, and two Nooter Eriksen HRSGs. In September 2002, in accordance with the Florida Electrical Power Plant Siting Act, previous owner Progress Energy submitted a petition for a determination of need for the third generation unit. In January 2003, the Florida Public Service Commission (FPSC) approved the petition to add the third generation unit. The company moved forward with plans to build a combined-cycle power unit— approximately 500-MW—to begin commercial operation in late 2005. The unit, fueled by low emission natural gas, gave Progress Energy about 1,500-MW of generation capacity at its Hines site.

Power Block 4 is home to two General Electric Frame 7FA combustion turbines, one GE D11 reheat steam turbine, and two Nooter Eriksen HRSGs. Power Block 4 is currently offline due to scheduled maintenance.

All units are equipped with Selective Catalytic Reductions (SCR) systems. By utilizing emission controls, the facility is able to reduce its NOx output.

The site includes more than 8,000 acres. However, the complex itself takes up about 200 acres, while a cooling pond in the back of the facility covers approximately 2,000 acres and uses 15 million gallons of water per day.

“We typically run about two-percent forced outages per year, throughout all units,” said Mike Rabs, maintenance supervisor for the site.

Duke Energy plans to invest approximately $160 million to install chilling units at the Hines Energy Complex by 2017. The addition will increase the facility’s output by about 220-MW, bringing the power plant’s total generating capacity to 2,132-MW.

Previously, the Hines Energy Complex was known as the Hines Energy Center when Progress Energy owned the facility. Duke Energy acquired Progress Energy in July 2013.

Prior to that, the site served as a phosphate mine. According to Duke Energy spokesman Sterling Ivey, phosphate still remains in the area.

The Hines Energy Complex provides about 30 percent of Duke Energy’s overall energy needs in Florida.

 

 

2014 Articles

Harvard Law School professor pays Clean Power Plan is unconstitutional

12/31/2014

Laurence H. Tribe, professor of constitutional law at Harvard University and former mentor to Barack Obama, said in an article last week that the EPA’s Clean Power Plan is unconstitutional.

3 SKorea workers die at nuke plant construction site

12/30/2014

SEOUL, South Korea (AP) — Three South Korean workers died Friday after apparently inhaling toxic gas at a construction site for a nuclear plant being built by South Korea's monopoly nuclear power company, which has come un...

UMaine in business of certifying turbine blades

12/30/2014

ORONO, Maine (AP) — The University of Maine has tested its largest wind turbine blade to date. UMaine's Advanced Structures and Composites Center completed static strength testing this month of a 184-foot-long wind turbine...

Mergers, EPA carbon plan generated much attention during 2014

12/29/2014

Mergers, the Environmental Protection Agency (EPA) Clean Power Plan, cheap natural gas and the polar vortex were among the most noteworthy generation stories of 2014.

Developer opens Ohio review for 800-MW, gas-fired project

12/29/2014

Clean Energy Future-Lordstown LLC plans an 800-MW, gas-fired power project, and on Dec. 24 applied with the Ohio Power Siting Board for certain routine waivers it needs before filing a full siting application for this proj...

New England utility exec named to Vermont PSB

12/29/2014

A woman who worked for Vermont's Department of Public Service for 17 years is going to become the next member of the utility-regulating Public Service Board. The appointment of Sarah Hofmann was announced Monday by Gov. Pe...

Brown picks aide to lead troubled California utility board

12/29/2014

Gov. Jerry Brown named a former adviser on Tuesday to be the next head of California's troubled utilities commission, replacing a regulatory chief accused of back-channel dealings with utilities. Michael Picker, a former a...

Washington state carbon emissions dropped in 2011

12/29/2014

Greenhouse gas emissions in Washington state dropped by about 4.6 percent between 2010 and 2011, led by reductions in emissions from the electricity sector, according to the latest figures released by the state. The latest...

Group wants state regulators recused from PNM case

12/29/2014

State regulators in less than two weeks are to begin deliberating a proposal that calls for shutting down part of an aging coal-fired power plant in northwestern New Mexico that serves more than 2 million customers in the ...

Vermont Yankee plant prepares to shut down

12/29/2014

The Vermont Yankee nuclear plant is getting ready to shut down. Its owner, Entergy Corp., says it is closing the plant for economic reasons. The plant in Vernon is expected to disconnect from the regional power grid Monday.

PSEG Solar to acquire Maryland solar project from juwi

12/23/2014

PSEG Solar Source will acquire a 12.9-MW solar energy facility near Waldorf, Maryland from juwi solar (JSI). The PSEG Waldorf Solar Energy Center will increase the capacity of PSEG Solar Source's portfolio to 123-MW.

PG&E discloses more emails with state regulators

12/23/2014

California's largest power utility released a dozen more emails Monday that it said showed improper back-channel discussions between the utility and top state regulators.

Indianapolis airport solar farm expansion completed

12/23/2014

Contractors have finished bringing online dozens of acres of solar panels at Indianapolis International Airport, solidifying its status as the home of the nation's largest airport-based solar farm.

French power company to pay $772M in bribery case

12/23/2014

A French power and transportation company has agreed to pay $772 million to resolve allegations that it bribed high-ranking foreign government officials for lucrative projects, the Justice Department said Monday.

Nebraska nuclear plant back online after short outage

12/23/2014

The Fort Calhoun nuclear power plant is back online less than a week after its main generator unexpectedly shut down as a precaution.

Ameren Missouri plans $135M in energy efficiency

12/23/2014

Missouri's largest electric company said Monday that it plans to invest $135 million in energy efficiency programs for customers over a three-year period.

TEPCO completes nuclear fuel assemblies removal from Fukushima 4

12/22/2014

Tokyo Electric Power Co. (TEPCO) said it has safely removed the fuel assemblies from the most damaged nuclear reactor at the Fukushima Daiichi nuclear power plant.

B&W Vølund to build waste-to-energy power plant in Scotland

12/22/2014

In a consortium with Interserve, Babcock & Wilcox Co.’s (B&W, NYSE:BWC) subsidiary, Babcock & Wilcox Vølund A/S (B&W Vølund), will engineer, procure and construct (EPC) a waste-to-energy (WTE) power plant f...

SKorea holds N-plant drills against cyber threats

12/22/2014

South Korea's monopoly nuclear power company said it began drills Monday against possible cyberattacks after online threats of attack against its plants.

PSC approves solar power project

12/22/2014

The Public Service Commission has approved solar power project planned by Kentucky Utilities and Louisville Gas and Electric in Mercer County.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...