Work to resume at Brazil's 11.2 GW Belo Monte electric plant

by HydroWorld.com staff

Just two weeks after a federal court shut down progress on the 11.2-GW Belo Monte hydropower project, a Supreme Court decision has overturned this work stoppage.

HydroWorld.com reported earlier this month that a Brazilian federal court suspended development of the $17 billion project, saying indigenous people had not been properly consulted.

However, Brazil's most recent Supreme Court decision overturns that ruling, saying local communities should have had the right to voice their opinions on the environmental impact of the Belo Monte hydropower project before it was approved by the country's congress.

The decision could be revised again as the Supreme Court examines more evidence.

The controversial hydroelectric facility has seen other work stops since construction began in 2011, including one caused by a strike in April.

Read more Latin America hydro news

This story was originally published on HydroWorld.com and was republished with permission.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...