Financing locked in for wind power project in Kansas

CPV Renewable Energy Co. on Jan. 10 said it closed financing for the construction of its 165.6 MW Cimarron Wind Energy Project in Kansas. The company began construction of the project in early December 2011 and expects that the Cimarron project will achieve commercial operation in November 2012.

The project's 72 Siemens (NYSE: SI) 2.3 MW turbines will supply Tennessee Valley Authority (TVA) customers with energy under a 20-year power purchase agreement. CPV Renewable Energy was awarded the power purchase agreement as part of TVA's 2009 Request for Proposals for renewable generation. The project is managed by a CPV affiliate, is being constructed by Wanzak Construction, and will be operated by North American Energy Services.

Coordinating Lead Arrangers Bank of Tokyo Mitsubishi UFJ and Union Bank of California were joined by Mandated Lead Arrangers Helaba, Siemens Financial Services and Lloyds in providing $262.8 million of senior credit facilities.

Read more financial news

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...