Wind project picks Vestas turbines

Green Mountain Power announced that it has selected the Vestas V112 3 MW turbine for the $150 million, 63 MW Kingdom Community wind project to be built in Lowell, Vt.

The turbine choice was identified in a filing Green Mountain Power made on June 6 with the Vermont Public Service Board of several of the documents required before construction of the project can begin.

Green Mountain Power is cooperating on the project with local utility Vermont Electric Co-op.

Construction of the new facility is expected to finish by December 2012 in order to qualify for $40 million in federal production tax credits.

Read more wind energy news

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...