Emerson notches $95m order to modernize Europe’s largest power plant

Emerson Process Management has secured a $95m contract with Polish utility Polska Grupa Energetyczna to modernize six generating units at the Belchatow coal fired power plant.
As both the main automation and electrical contractor, it will be responsible for project management, procurement, engineering, design, installation and implementing new instrumentation, control and electrical subsystems.
Emerson won contracts in 2007 and 2009 to assist with earlier phases of Polska Grupa Energetyczna's modernization programme. The company did not say when it expected the renovation to be completed.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...