NRG gas plant in New York

The New York State Public Service Commission has approved the construction of a 1,040 MW gas-fired power plant.

NRG Astoria, a subsidiary of NRG Energy, Inc., plans to build the $1.4 billion combined-cycle plant to replace an older 600 MW facility.

NRG Astoria intends to develop, finance, construct and operate the project as a merchant developer without relying upon cost-of-service rates set by either a federal or state regulatory entity.

The power plant will be built in two phases. The first phase involves the replacement of seven simple-cycle peaking generators that have a combined rated capacity of 120 MW, with two combined-cycle units capable of providing a total of 520 MW of electricity. The second phase involves the replacement of 24 simple-cycle units that have a combined capacity of 480 MW, with two combined-cycle units identical to those involved in the first phase.

Construction is expected to last 30 months for both phases, with phase one being completed in 2013 and the second phase in 2015.

NRG expects to finance each phase separately through a combination of debt and equity.

Read more gas-fired news and features

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...