Construction nears for Hillabee expansion project

Williams Partners LP expects to begin construction in May on its Hillabee natural gas pipeline expansion project, recently approved by the US Federal Energy Regulatory Commission. The first phase of the project is expected to go into service in May 2017.

The project involves the expansion of Williams Partners’ Transco pipeline system to serve gas markets in Florida.

The first phase will provide incremental firm capacity from certain receipt points at Transco’s Station 85 in Choctaw County, Ala., to a proposed point of interconnection between Transco and the Sabal Trail Pipeline in Tallapoosa County, Ala.

Sabal Trail will acquire by lease 100% of such capacity on a long-term basis.

To be constructed in three phases, the Hillabee expansion is designed to add a total of 1.13 million dekatherms/day of gas pipeline capacity to the Transco system by May 2021.

The expansion involves the construction of 43 miles of additional pipe segments—or loops—in Alabama, a new compressor facility in Choctaw County, Ala., as well as modifications to other existing compressor stations and valve sites.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now


Making DDoS Mitigation Part of Your Incident Response Plan: Critical Steps and Best Practices

Like a new virulent strain of flu, the impact of a distributed denial of service (DDoS) attack is...

The Multi-Tax Challenge of Managing Excise Tax and Sales Tax

To be able to accurately calculate multiple tax types, companies must be prepared to continually ...

Operational Analytics in the Power Industry

Cloud computing, smart grids, and other technologies are changing transmission and distribution. ...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...