Santos Gladstone LNG project reaches another milestone

The Santos Ltd.-operated Gladstone LNG project has passed another milestone with the final section of the coal seam gas supply transmission pipeline now laid through a tunnel underneath Gladstone harbor to the LNG plant site on Curtis Island.

One hundred and twenty pipe segments, each 36 m long, were welded and gradually pushed through the 4.3-km tunnel using a large hydraulic jack.

The tunnel was first filled with seawater to give buoyance to the 42-in. line as it was pushed through.

The operation brings the 420-km supply pipeline from fields in the Surat and Bowen basins of central-eastern Queensland to its final stages of construction.

The marine crossing pipe will now be connected to the buried mainland and island sections of the line.

Saipem Australia was the pipeline contractor while Theiss was responsible for the tunnel construction.

Pipeline precommissioning works are under way with 50% of the required hydrotesting completed.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...