Downstream cost index reaches record high

By OGJ editors
HOUSTON, June 30
-- Design and construction costs for refining and petrochemical projects rose for the fourth consecutive 6-month period to a record high, according to the IHS CERA Downstream Capital Costs Index.

The proprietary index, which uses 2000 as the base year with a value of 100, rose to 192 in the first quarter of 2011 from 180 in the third quarter of 2010 (OGJ, Nov. 29, 2010, Newsletter).

The 6% increase was the largest rise since the previous peak in third-quarter 2008.

A 12% rise in steel costs strongly influenced the recent surge and helped push up equipment costs.

Other cost increases included construction labor 8% and engineering and project management 5%.



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...