Downstream cost index reaches record high

By OGJ editors
HOUSTON, June 30
-- Design and construction costs for refining and petrochemical projects rose for the fourth consecutive 6-month period to a record high, according to the IHS CERA Downstream Capital Costs Index.

The proprietary index, which uses 2000 as the base year with a value of 100, rose to 192 in the first quarter of 2011 from 180 in the third quarter of 2010 (OGJ, Nov. 29, 2010, Newsletter).

The 6% increase was the largest rise since the previous peak in third-quarter 2008.

A 12% rise in steel costs strongly influenced the recent surge and helped push up equipment costs.

Other cost increases included construction labor 8% and engineering and project management 5%.



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...