Golden Pass LNG terminal commissions Phase 2

By OGJ editors
HOUSTON, May 11
-- Golden Pass LNG Terminal LLC, Houston, announced it has received approval from the US Federal Energy Regulatory Commission to place Phase 2 of the Sabine Pass, Tex., terminal’s capacity into service.

The operator completed Phase 2 commissioning and performance tests in late April, having previously commissioned Phase 1 in early March (OGJ Online, Mar. 17, 2011). Also placed into service was the 69-mile Golden Pass takeaway pipeline to move gas from the terminal to downstream interstate markets.

Combined Phase 1 and 2 operations will enable nominal sendout capacity of more than 2 bcfd and regasification capacity of 15.6 million tonnes/year of LNG. The pipeline can move as much as 2.5 bcfd of natural gas.



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...

Reduce Engineering Project Complexity

Engineering document management presents unique and complex challenges. A solution based in Enter...

Revolutionizing Asset Management in the Electric Power Industry

With the arrival of the Industrial Internet of Things, data is growing and becoming more accessib...