Aramco picks NGL project EPC

By OGJ editors
HOUSTON, Mar. 16
-- Saudi Aramco has awarded four lump-sum turnkey contracts for the Shaybah NGL project to Samsung Engineering Co. Ltd. to perform engineering, procurement, and construction.

Scope of this award includes construction of the inlet facilities, NGL-recovery trains, dehydration, residue-gas compression, acid-gas compression, NGL storage and shipping, the upgrade of the gas-handling capacity for the four existing Shaybah gas-oil separation plants, and other associated facilities.

It also includes a major upgrade to increase the power-generation capacity to more than 1 Gw by installing four cogeneration units, seven single-cycle units, a 50-km, 230 kv transmission line, and associated electrical and nonelectrical utilities.

Aramco is building a grassroots NGL recovery plant at Shaybah field in Rub’ al-Khali, also known as the “Empty Quarter.”



Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...