Santos expects first LNG from Queensland's GLNG project in third quarter

Santos Ltd. says that its GLNG project in Queensland, Australia, is approaching 95% completion and that it is expected to produce first liquefied natural gas (LNG) around the end of the third quarter of this year.

Progress on the GLNG project includes:

  • Construction completed for all major gas field processing facilities
  • Completion of 261-mile (420-kilometer) pipeline, including a 2.6-mile (4.3-kilometer) undersea pipeline tunnel
  • Installation of all 111 modules that make up its two LNG processing trains
  • Hydrotesting of both LNG storage tanks
  • Construction completed of the project’s LNG loading jetty
  • Introduction of first gas into the plant and lighting of the flare
  • Successful firing of the first two gas turbine generators

Previous guidance for first LNG was in the second half of this year. The project is progressing on time and within its $18.5 billion budget.

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...