VAALCO takes action on Avouma ESP failures

Offshore staff

HOUSTONVAALCO Energy’s production offshore Gabon declined during 3Q, mainly due to continuing electrical submersible pump (ESP) failures at the Avouma field.

The company is mobilizing a hydraulic workover unit onto the Avouma platform to remove the ESPs so that the manufacturer can analyze the cause of the failure.

VAALCO is working on a plan to replace the pumps in the affected wells and anticipates restoring at least part of the shut-in production by year-end.

It estimates its net share of the cost at around $3.1 million.

11/10/2016

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Storm Impact Analytics for Utilities

In recent years, increasingly volatile and extreme weather events have significantly impacted the...

Reach New Heights: Six Best Practices in Planning and Scheduling

These 6 best practices have created millions of dollars in value for many global companies. Learn...

Making DDoS Mitigation Part of Your Incident Response Plan: Critical Steps and Best Practices

Like a new virulent strain of flu, the impact of a distributed denial of service (DDoS) attack is...

The Multi-Tax Challenge of Managing Excise Tax and Sales Tax

To be able to accurately calculate multiple tax types, companies must be prepared to continually ...