South Pars 17 platform awaiting load out

Offshore staff

TEHRAN, Iran – The final two satellite platforms for the South Pars phases 17 and 18 development projects in the Persian Gulf should be loaded out soon from the Bandar Abbas Industrial Yard.

Project spokesman Hassan Boveiri told news service Shana that Platform 17B, which weighs 2,300 tons, will be able to recover 500 MMcf/d and export it to onshore refining facilities. 

Installation offshore should be completed on Nov. 10, the final stage of development of the two phases. 

Platform 17B, the fourth platform for phases 17/18, is under construction by Iran Shipbuilding & Offshore Industries Complex Co.


Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now


Making DDoS Mitigation Part of Your Incident Response Plan: Critical Steps and Best Practices

Like a new virulent strain of flu, the impact of a distributed denial of service (DDoS) attack is...

The Multi-Tax Challenge of Managing Excise Tax and Sales Tax

To be able to accurately calculate multiple tax types, companies must be prepared to continually ...

Operational Analytics in the Power Industry

Cloud computing, smart grids, and other technologies are changing transmission and distribution. ...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...