All wells drilled from South Pars platform 24B

Offshore staff

TEHRAN, IranPetro Gohar Farasahel Kish Co. (PGFK) has completed drilling of eight wells for platform 24B for phases 22-24 of the South Pars field in the Persian Gulf.

Drilling took less than 20 months to complete, according to managing director Masood Ziari, and on average 71.8 days per well. Earlier this year PGFK completed drilling from platform 24A.

Records established at 24B included drilling a 32-in. section in nine hours. Some of the wells featured a 60° angle.

Phases 22, 23, and 24 are being developed via two main platforms (22 and 23) and two satellite platforms (24A and 24B). PGFK is drilling a total of 38 wells. The campaign will add 1 bcf/d gas to production capacity at South Pars. 

All platforms are expected to be operational by October 2017.

10/31/2016

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Logistics Risk Management in the Transformer Industry

Transformers often are shipped thousands of miles, involving multiple handoffs,and more than a do...

Secrets of Barco UniSee Mount Revealed

Last year Barco introduced UniSee, a revolutionary large-scale visualization platform designed to...

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...