Phase 17 platform, wells nearing completion at South Pars offshore Iran

Offshore staff

TEHRAN, Iran – Construction of platform 17B for phases 17 and 18 of the South Pars gas field is 88% complete, and the structure should be loaded out of the Bandar Abbas yard by late September, according to news service Shana.

Offshore installation should follow during October.

Platform 17B is set to start production by next February: the 11-well drilling campaign is virtually complete.

Phases 17 and 18 should add 56 MMcm/d (2 bcf/d) to Iran’s daily gas output.

08/03/2016

Share your news with Offshore at news@offshore-mag.com

Platform 17B for phases 17 and 18 of the South Pars gas field offshore Iran
(Courtesy Shana)

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

The Time is Right for Optimum Reliability: Capital-Intensive Industries and Asset Performance Management

Imagine a plant that is no longer at risk of a random shutdown. Imagine not worrying about losing...

Going Digital: The New Normal in Oil & Gas

In this whitepaper you will learn how Keystone Engineering, ONGC, and Saipem are using software t...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...

Leveraging the Power of Information in the Energy Industry

Information Governance is about more than compliance. It’s about using your information to drive ...