TEHRAN, Iran – Construction of platform 17B for phases 17 and 18 of the South Pars gas field is 88% complete, and the structure should be loaded out of the Bandar Abbas yard by late September, according to news service Shana.

Offshore installation should follow during October.

Platform 17B is set to start production by next February: the 11-well drilling campaign is virtually complete.

Phases 17 and 18 should add 56 MMcm/d (2 bcf/d) to Iran’s daily gas output.

08/03/2016

Share your news with Offshore at news@offshore-mag.com

Platform 17B for phases 17 and 18 of the South Pars gas field offshore Iran
(Courtesy Shana)

Did You Like this Article? Get All the Energy Industry News Delivered to Your Inbox

Subscribe to an email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

Whitepapers

Making DDoS Mitigation Part of Your Incident Response Plan: Critical Steps and Best Practices

Like a new virulent strain of flu, the impact of a distributed denial of service (DDoS) attack is...

The Multi-Tax Challenge of Managing Excise Tax and Sales Tax

To be able to accurately calculate multiple tax types, companies must be prepared to continually ...

Operational Analytics in the Power Industry

Cloud computing, smart grids, and other technologies are changing transmission and distribution. ...

Maximizing Operational Excellence

In a recent survey conducted by PennEnergy Research, 70% of surveyed energy industry professional...